Parsvnath Builders asked to refund Rs 46 lakh to buyer for project delay

The commission has also allowed Rs 25,000 as litigation charges to Dev, a central Delhi resident. Representative image
The Delhi state consumer commission has directed a real estate firm to pay Rs 3 lakh as compensation to a homebuyer for delay in handing over the possession of a flat.

The Delhi State Consumer Disputes Redressal Commission also asked Parsvnath Developers Ltd to refund Rs 46,28,933 to Varun Dev, who had paid the amount for a flat in Ghaziabad, while rejecting the builder's claim that global recession had slowed the construction of its various projects.

"Sole defence raised by the firm in not handing over the physical possession of the flat is 'global recession'. No material has been placed on record by the firm to support his contention that there was a 'global recession' which resulted into non-completion of the project," the bench, comprising judicial member N P Kaushik, said.

The commission has also allowed Rs 25,000 as litigation charges to Dev, a central Delhi resident.

According to the complaint filed by Dev, he entered into an agreement in 2008 with the firm for the construction of a flat in one of its projects named 'Parsvnath Exotica' in Ghaziabad.

It said that the complainant made various payments from time to time totaling to an amount of Rs 46,28,933.

It further claimed that when he visited the site in the year 2009 there was no construction activity.

The firm claimed that global recession had slowed the construction of its various projects.

The company also claimed that there were many other reasons related to various governmental authorities which further delayed the construction.

The commission rejected these contentions, saying the firm has failed to provide any evidence for the same.

(Only the headline and picture of this report may have been reworked by the Business Standard staff; the rest of the content is auto-generated from a syndicated feed.)

Dear Reader,


Business Standard has always strived hard to provide up-to-date information and commentary on developments that are of interest to you and have wider political and economic implications for the country and the world. Your encouragement and constant feedback on how to improve our offering have only made our resolve and commitment to these ideals stronger. Even during these difficult times arising out of Covid-19, we continue to remain committed to keeping you informed and updated with credible news, authoritative views and incisive commentary on topical issues of relevance.

We, however, have a request.

As we battle the economic impact of the pandemic, we need your support even more, so that we can continue to offer you more quality content. Our subscription model has seen an encouraging response from many of you, who have subscribed to our online content. More subscription to our online content can only help us achieve the goals of offering you even better and more relevant content. We believe in free, fair and credible journalism. Your support through more subscriptions can help us practise the journalism to which we are committed.

Support quality journalism and subscribe to Business Standard.

Digital Editor

Business Standard is now on Telegram.
For insightful reports and views on business, markets, politics and other issues, subscribe to our official Telegram channel