IPP's thermal power projects in trouble with 60,000-Mw stressed assets

Nearly 60,000 mw of thermal power projects in the IPP (independent power producers) segment are stressed mainly for want of long-term power purchase pacts and unavailability of domestic gas supplies, says a report.

According to a report by rating agency Icra, the overall stressed thermal power generation assets remain a sizeable 60,000 mw. Of this about 26,000 mw are in trouble due to the absence of long-term PPAs (power purchase agreements), about 12,000 mw are stranded due to non-availability of domestic gas supply and 22,000 mw due to unviable tariff in the PPAs and capital cost overrun.

The report said the weak financials of state-owned discoms constrain their paying capacity, which along with subdued demand from the industrial segment has affected the demand growth.

"As a result, the overall progress in signing of long-term PPAs through competitive bidding by state-owned discoms remains slow," it said.

The agency said that the 26,000-mw capacity, which does not have long-term PPAs, remains exposed to price and volume risks in the short-term trading market.

"About 60 per cent of this capacity is operational and the balance is under implementation," the report said.

Icra further said the Supreme Court judgement of April 11 this year which disallowed tariff relief to Adani Power and Coastal Gujarat Power of the Tatas and other imported coal-based projects due to change in regulations in Indonesia has impacted a total capacity of 9,000 mw.

"Many of the recently commissioned and under- construction projects with competitively bid-based PPAs remain exposed to the risk of under-recovery of fixed charges due to increase in capital costs following execution delays, exchange rate volatility, funding problems and limited nature of the competitively bid-based tariffs," it said.

The report also noted that gas-based generation capacity of about 12,000 mw in the IPP segment is either stranded or under-utilised due to non-availability of domestic gas and reluctance on the part of the state-run discoms to procure power from them, using imported regasified liquefied natural gas citing higher cost.


Dear Reader,


Business Standard has always strived hard to provide up-to-date information and commentary on developments that are of interest to you and have wider political and economic implications for the country and the world. Your encouragement and constant feedback on how to improve our offering have only made our resolve and commitment to these ideals stronger. Even during these difficult times arising out of Covid-19, we continue to remain committed to keeping you informed and updated with credible news, authoritative views and incisive commentary on topical issues of relevance.

We, however, have a request.

As we battle the economic impact of the pandemic, we need your support even more, so that we can continue to offer you more quality content. Our subscription model has seen an encouraging response from many of you, who have subscribed to our online content. More subscription to our online content can only help us achieve the goals of offering you even better and more relevant content. We believe in free, fair and credible journalism. Your support through more subscriptions can help us practise the journalism to which we are committed.

Support quality journalism and subscribe to Business Standard.

Digital Editor

Business Standard is now on Telegram.
For insightful reports and views on business, markets, politics and other issues, subscribe to our official Telegram channel