Lucknow Metro successfully conducts load testing

The Lucknow Metro Rail Corporation (LMRC) on Friday successfully conducted load testing of two metro trains on the remaining section of the North-South corridor, an official said.

The metro trains were run on viaduct.

This is being seen by many technical experts here and elsewhere in the country as yet another milestone for the 22.878 km long corridor from the Chowdhary Charan Singh International Airport to Munshipulia.

The trains rolled out from Charbagh at 6.30 a.m. and reached the newly constructed 177 meter-long balanced cantilever bridge over Gomti River where they will stay for 24 hours for load testing.

After the load testing, the metro trains will move to the 60 Meter Special Steel Span near Nishatganj and will stay there again for 24 hours, the official told IANS.

The metro trains will be back in Charbagh on December 31 after completing all the necessary tests and trials.

"All efforts are being made by the LMRC to commence signalling trials and integrated testing and commissioning trials on the balance section of the North-South corridor (Phase 1-A) so as to commission it as per the target stipulated by the government," added the official.

To make the test possible, LMRC has recently completed the work of Over Head Electrification (OHE) and charged the OHE at midnight to feed power supply to the traction.

The gigantic project has become a reality in record time.

Kumar Keshav, Managing Director of the LMRC said, "It is a great day for LMRC and I appreciate the extreme hard work and dedication of the whole team at LMRC, our contractors and others involved in completing this tough task in a very strict time frame."

The Metro work is likely to be completed by February, much ahead of the initial deadline of April 2019.

--IANS

md/oeb/sed


(This story has not been edited by Business Standard staff and is auto-generated from a syndicated feed.)


Dear Reader,


Business Standard has always strived hard to provide up-to-date information and commentary on developments that are of interest to you and have wider political and economic implications for the country and the world. Your encouragement and constant feedback on how to improve our offering have only made our resolve and commitment to these ideals stronger. Even during these difficult times arising out of Covid-19, we continue to remain committed to keeping you informed and updated with credible news, authoritative views and incisive commentary on topical issues of relevance.

We, however, have a request.

As we battle the economic impact of the pandemic, we need your support even more, so that we can continue to offer you more quality content. Our subscription model has seen an encouraging response from many of you, who have subscribed to our online content. More subscription to our online content can only help us achieve the goals of offering you even better and more relevant content. We believe in free, fair and credible journalism. Your support through more subscriptions can help us practise the journalism to which we are committed.

Support quality journalism and subscribe to Business Standard.

Digital Editor

Business Standard is now on Telegram.
For insightful reports and views on business, markets, politics and other issues, subscribe to our official Telegram channel