Chandrayaan 2: Vikram hard-landed within 500 meters of landing site: Govt

Topics Chandrayaan-2 | ISRO | ISRO Chief

Representative Image

Chandrayaan-2's Vikram lander hard-landed as reduction in velocity during its descent was more than the designed parameters, the government said on Wednesday throwing more light on ISRO's dashed hopes of making a soft landing on the lunar surface in its maiden attempt.

In a written reply to a question in the Lok Sabha, Jitendra Singh, the minister of state in the Prime Minister's Office, who looks after the department of space, said the first phase of descent was performed nominally from an altitude of 30 kms to 7.4 kms above the moon's surface and velocity was reduced from 1,683 metres per second to 146 metres per second.

"During the second phase of descent, the reduction in velocity was more than the designed value. Due to this deviation, the initial conditions at the start of the fine braking phase were beyond the designed parameters. As a result, Vikram hard-landed within 500 metres of the designated landing site," he said.

Singh, however, said most components of technology demonstration, including the launch, orbital critical maneuvers, lander separation, de-boost and rough braking phase were successfully accomplished.

With regards to the scientific objectives, all the eight state-of-the-art scientific instruments of the orbiter are performing according to the design and providing valuable scientific data. Due to the precise launch and orbital maneuvers, the mission life of the orbiter is increased to seven years, he said.

Data received from the orbiter is being provided continuously to the scientific community, he said, adding the same was recently reviewed in an all-India user meet organized in New Delhi.

The indigenously developed Chandrayaan-2 spacecraft comprising of orbiter, lander and rover was successfully launched on-board the indigenous GSLV MK III-M1 Mission on July 22.

After accomplishing four earth bound maneuvers and trans-lunar injection, the spacecraft was successfully inserted in the lunar orbit on August 20. A series of moon-bound maneuvers were then carried out to achieve a Lunar orbit of 119 x 127 km.

The Lander 'Vikram' was separated, as planned, from the Orbiter on September 2 2019. After two successful de-orbiting maneuvers, powered descent of the lander was initiated on September 7 to achieve soft landing on the moon surface.



Dear Reader,


Business Standard has always strived hard to provide up-to-date information and commentary on developments that are of interest to you and have wider political and economic implications for the country and the world. Your encouragement and constant feedback on how to improve our offering have only made our resolve and commitment to these ideals stronger. Even during these difficult times arising out of Covid-19, we continue to remain committed to keeping you informed and updated with credible news, authoritative views and incisive commentary on topical issues of relevance.

We, however, have a request.

As we battle the economic impact of the pandemic, we need your support even more, so that we can continue to offer you more quality content. Our subscription model has seen an encouraging response from many of you, who have subscribed to our online content. More subscription to our online content can only help us achieve the goals of offering you even better and more relevant content. We believe in free, fair and credible journalism. Your support through more subscriptions can help us practise the journalism to which we are committed.

Support quality journalism and subscribe to Business Standard.

Digital Editor

Business Standard is now on Telegram.
For insightful reports and views on business, markets, politics and other issues, subscribe to our official Telegram channel