Work begins on construction of Delhi Metro Phase-IV first corridor

The civil work on construction of the 10 stations is expected to be completed in 30 months.

After a long wait, work began on the construction of Delhi Metro's Phase-IV project with a groundbreaking ceremony held at Haider Badli Mor here on Monday, officials said.

Piling work began for construction of 10 stations of 28.92-km Janakpuri West-R K Ashram Marg corridor, they said.

"This corridor is an extension of the Magenta Line and will have a total of 22 stations. The tenders for the remaining stations are also nearing finalisation," Executive Director Corporate Communications, DMRC, Anuj Dayal said.

The civil work on construction of the 10 stations is expected to be completed in 30 months, he said.

The stations on this entirely elevated section are Keshopur, Paschim Vihar, Peeragarhi, Mangolpuri, West Enclave, Pushpanjali, Deepali Chowk, Madhuban Chowk, Prashant Vihar and North Pitampura.

The Union Cabinet, in a meeting chaired by Prime Minister Narendra Modi, in March had approved three out of the six corridors of the Delhi Metro's proposed Phase-IV which will further improve connectivity in the national capital.

According to the government, the Mukundpur-Maujpur, R K Ashram-Janakpuri West and Aero City-Tughlakabad corridors were approved by the cabinet.

A groundbreaking ceremony was held next to the Haiderpur Badli Mor station of the Yellow Line in the presence of DMRC chief Mangu Singh and other senior officials of the Delhi Metro.

"A huge office has been set up at Haiderpur Badli Mor station to monitor the construction of the Phase-IV work," Dayal told PTI.

"As part of the first corridor work, three interchange stations -- Peeragarhi (with Green Line), Madhuban Chowk (with Red Line) and Haiderpur Badli Mor (with Yellow Line) -- will come up. In addition, the entire Janakpuri West-R K Ashram Marg corridor will have three more interchange facilities at Majlis Park (Pink Line), Azadpur (with Yellow Line) and R K Ashram Marg (with Blue Line)," Dayal said.

Therefore, the new corridor in total will have six interchange stations.

"The Phase-IV of the Delhi Metro project comprising three corridors covering 61.67 km and today is a landmark day for the DMRC," Dayal said.

"The first phase of construction of the Delhi Metro had started on October 1, 1998 and since then the DMRC has established itself as the most reliable public transportation system in the national capital and its peripheries. During these two decades, the Delhi Metro project has also emerged as one of the fastest executed metro projects anywhere in the world," he said.

The first three phases have interconnected cities in the NCR and helped in reducing traffic congestion and pollution in the city, he added.

The other three proposed corridors of Phase-IV which have not yet been approved by the Union Cabinet are Rithala-Bawana-Narela, Inderlok-Indraprastha and Lajpat Nagar-Saket G Block.



Dear Reader,


Business Standard has always strived hard to provide up-to-date information and commentary on developments that are of interest to you and have wider political and economic implications for the country and the world. Your encouragement and constant feedback on how to improve our offering have only made our resolve and commitment to these ideals stronger. Even during these difficult times arising out of Covid-19, we continue to remain committed to keeping you informed and updated with credible news, authoritative views and incisive commentary on topical issues of relevance.

We, however, have a request.

As we battle the economic impact of the pandemic, we need your support even more, so that we can continue to offer you more quality content. Our subscription model has seen an encouraging response from many of you, who have subscribed to our online content. More subscription to our online content can only help us achieve the goals of offering you even better and more relevant content. We believe in free, fair and credible journalism. Your support through more subscriptions can help us practise the journalism to which we are committed.

Support quality journalism and subscribe to Business Standard.

Digital Editor

Business Standard is now on Telegram.
For insightful reports and views on business, markets, politics and other issues, subscribe to our official Telegram channel